News in English     | 30.08.2024. 12:43 |

Banja Luka Court annuls the approval for the construction of Dabar hydropower plant 

FENA Press release, Photo: Aarhus center in BiH

SARAJEVO, August 30 (FENA) - The District Court in Banja Luka ruled in favor of the "Resource Aarhus Center in BiH" Association from Sarajevo, annulling the decision issued by the Ministry of Spatial Planning, Construction and Ecology of the Republika Srpska. The contested decision approved the construction of the infrastructure facilities of the Dabar hydropower plant from Trebinje, on the Zalomka River, within the Upper Horizons (Gornji horizonti) project. The Center also appealed this Decision for the Environment from Banja Luka.

Sadržaj dostupan isključivo pretplatnicima FENA servisa. Za više informacija o načinu i uslovima korištenja servisa kontaktirajte marketing@fena.ba.

(FENA) A. B.

Vezane vijesti

Constitutional Court of RS declares Mount Jahorina regulatory plan unconstitutional

Aarhus Center in BiH: Suspicious rehabilitation activities on the Kraljuštica river

Aarhus Center in BiH: Water permit for the quarry construction project in Špionica annulled

Promo

MBL Balkans 2025 - Telemach fondacija priredila izlet u Sarajevo za mlade matematičke genijalce

Potražite u m:tel ponudi Xiaomi 15 i Xiaomi 15 Ultra s vrijednim poklonom!

m:tel: Pozovite 1411 i pružite podršku Sigurnim kućama!